Division of Petroleum & Chemical Safety

 

Facility: 3034795 Tank: 5

Click for Facility/Tank Ownership history

Capacity: 13000
Product: E85
Status: Currently in use
Regulated Status Federal
OSFM First Notify Date: 3/6/2009
Current Age: 18
Install Date: 10/19/2006
Last Used Date:
Product Date: 10/19/2006
Petroleum Use:
CERCLA Substance:
CAS Code:
Removed Date:
Abandoned Material:
Abandoned Date:
Red Tag Issue Date:
Fee Due: $0.00
UL Number

Equipment Information

Equipment Type Equipment Install Date Last Passing Test Date Test Expire Date Failed Test Date
Corrosion Prot - Piping Fiberglass Non-Corrosive N/A N/A
Corrosion Prot - Tank Fiberglass Non-Corrosive N/A N/A
Leak Detect - Piping Mechanical Pressurized Line Leak Detection 7/12/2023 9/12/2024 9/12/2025
Leak Detect - Tank Automatic Tank Gauging Veeder Root TLS 350 with CSLD 9/12/2024 9/12/2025
Overfill Prev Device Overfill Alarm 9/12/2024 9/12/2027
Piping Fiberglass Double Wall Ameron Dualoy 3000/LCX N/A N/A
Piping Not Installed STP/Tanktop Sump N/A N/A
Spill Contain Device Single Wall Spill Bucket 9/12/2024 9/12/2027
Tank Fiberglass Single Wall Containment Solutions N/A N/A

Latest Blended Fuel Compatibility Form

File Name Status Status Date
CompatibilityFormSummary01172024-112201.pdf Approved 1/17/2024

Compatibility Form Attachments

File Name Description
veeder-root.pdf ATG Probe
Wayne Ovation fuel dispenser 1.pdf Dispenser
ameron piping e85.pdf Fiberglass Double Wall
containment solutions.pdf Fiberglass Single Wall
Flexsteel® Futura™ Ethan-ALL™ Dispensing Hose Assembly _ Chemical Transfer & Petroleum Hoses _ Industrial Hoses _ Continental Industry.pdf Hose
mld.pdf Mechanical Pressurized Line Leak Detection
11a-and-11b-automatic-nozzles.pdf Nozzle
veeder-root.pdf Overfill Alarm
flex connector e85.pdf Shear Valve
spill containers.pdf Single Wall Spill Bucket
spill containers.pdf Single Wall UDC Sump
stp.pdf Submersible Turbine Pump
mld.pdf TLS350

Additional Tests

Equipment Type Equipment Test Type Test Result Test Date History
Piping Fiberglass Double Wall Ameron Dualoy 3000/LCX Precision Test (Piping) Pass 9/12/2024 Show History