Notice of Violatlions (Current)
NOV Number:
E0020252301
(Pending)
Issue Date:
9/3/2025
Expiration Date:
11/2/2025
View NOV Form
Tanks |
Violations |
6 |
Overfill prevention equipment inspection(s) not completed (Required every 3 years). - E-85 drop tube still needs to be tested. |
1, 2, 3, 4, 5, 6 |
Piping interstitial must be open in all sumps - The dispenser product piping sump jumper tubes shall be removed or the product piping test boots pulled back after testing to allow the interstice to be open to the sump sensors. 175.420 b) |
1, 2, 3, 4, 5 |
Spill prevention equipment contains liquid/debris and must be cleared of materials and maintained clean and dry. |