Facility |
A/B operator retraining required as a result of issuance of the Notice of Violation |
5 |
Dispensers - hose breakaways are missing or leaking |
2, 3, 4, 5 |
Piping interstitial must be open in all sumps - Dispensers 1/2, 3/4, 5/6, 7/8, 9/10, 11/12, 13/14, 15/16, 17, 18 |
2, 3, 4, 5 |
Precision tank test required. - A tank precision test is required because of missing passing monthly leak reports. |
2, 3, 4, 5 |
Required monthly tank leak test records not available. - Missing monthly passing reports for the last ten months. |
2, 4, 5 |
Spill prevention equipment contains liquid/debris and must be cleared of materials and maintained clean and dry. |