1, 2 |
Dispensers - hoses cracked, split or worn and require replacement - Replace gasoline main hose on dispenser 12. |
Facility |
Financial responsibility must be reported yearly - The Notification Form is available at: https://webapps.sfm.illinois.gov/USTPortal/NotificationForm. This form is required to be submitted within 30 days of an ownership change. |
1, 2, 3 |
Line interstitial sensors have been raised and rendered inoperational. - Interstitial sensor(s) has/have been raised rendering it/them ineffective. Repair/replace sensor(s) into proper location so that it can function as designed. All STP sumps have sensors on the manway. Sensors must be in the lowest part of sump or per manufactures specifications. |
1, 2 |
Line leak detection equipment in alarm or failed test, must repair or replace. - Veeder Root is in alarm. L2 North Center Dispenser (5/6). Repair or replace sensor and clear ATG of alarms. |
3 |
Miscellaneous - Main diesel dispenser on truck side has a slight leak under dispenser. |
1, 2, 3 |
Piping interstitial must be open in all sumps - 175.420 b) Unless otherwise required by the manufacturer, the dispenser product piping sump jumper tubes shall be removed or the product piping test boots pulled back after testing to allow the interstice to be open to the sump sensors. This is for all sumps. |
1 |
Precision tank test required. - Tank 1 is not on monthly sensor reports. |
1 |
Tank monitor does not appear to function properly and requires maintenance. - Tank 1 regular annular sensor is not shown on the Veeter Root. All sensors must be shown on the ATG. |