Annual Emergency Stop Inspection not completed or inspection report not available. - All emergency shutoff switches shall be tested annually to verify they shut down all STPs or dispensers. Perform test, complete form (form is available at www.sfm.illinois.gov) and maintain on site with other annual testing documentation. |
6 |
Annual leak detection certification not completed (Required annually). - Annual leak detection certification (interstitial sensors/ATG) not completed. Testing shall be completed and submitted to OSFM. |
6 |
Annual leak detection certification not completed (Required annually). - Annual leak detection certification (leak detectors and/or interstitial sensors) not completed. Testing shall be performed. |
7 |
Annual leak detection certification not completed (Required annually). - Annual leak detection certification (interstitial sensors/ATG) not completed. Testing shall be completed and submitted to OSFM. |
7 |
Annual leak detection certification not completed (Required annually). - Annual leak detection certification (leak detectors and/or interstitial sensors) not completed. Testing shall be performed. |
8 |
Annual leak detection certification not completed (Required annually). - Annual leak detection certification (interstitial sensors/ATG) not completed. Testing shall be completed and submitted to OSFM. |
8 |
Annual leak detection certification not completed (Required annually). - Annual leak detection certification (leak detectors and/or interstitial sensors) not completed. Testing shall be performed. |
6, 7, 8 |
Document that emergency shut-off (shear valves) are in proper working order - Provide documentation that annual testing of all shear valves has been conducted and passed. |
7 |
Install drop tube vlave. - Regular south has stick in drop tube. Stick must be removed and make sure overfill drop tube valve is not damaged. |
6, 7, 8 |
Line interstitial sensor functional test not accomplished (Required annually). - Annual leak detection certification (leak detectors and/or interstitial sensors) not completed. Testing shall be performed. |
Facility |
Miscellaneous - Emergency shut off switch at control station is blocked with tobacco products. Display must be moved or emergency shut off switch moved to an open unobstructed location. |
Facility |
Miscellaneous - Emergency shut off switch must have a sign stating "Fuel Emergency Shut Off" with letters 2" in height. |
Facility |
Missing copies of Annual Walkthrough Inspection Report. - Annual Walkthrough by a licensed contractor shall be conducted and documentation maintained on site. |
6, 7, 8 |
Spill prevention equipment contains liquid/debris and must be cleared of materials and maintained clean and dry. - Spill buckets must be kept clean and dry. |
6, 7, 8 |
Tank interstitial sensor functional test not accomplished (Required annually). - Annual leak detection certification (interstitial sensors/ATG) not completed. Testing shall be completed and submitted to OSFM. |
8 |
Tank monitor does not appear to function properly and requires maintenance. - Tank 8 premium did not shown up on Veeder Root when I first printed inventory and testing from Veeder Root. I went through the Veeder Root and reprinted the inventory and testing and all three tanks printed properly. Contractor |